Construction Activity Reporting Schedule

Date: 18th March 2024.

Site Construction Activities

Block C (Philip Ozuah’s Block)
Update: Upon the completion of the casting of the first-floor slab, the contractor has commenced placing the steel reinforcement for the columns to support the second-floor slab. Steel reinforcements for the columns are to support the second-floor slab.
The situation with Timeline:
As of the 11th - 15th of March, the casting of the first-floor slab has been completed.

Pictures of Work done on site

 

Block D (TY Danjum Block)

Update: The casting of the ground beam of the foundation is still ongoing

The situation with Timeline:

As of the 11th - 15th of March, the casting of the ground beam of the foundation has reached 80% completion.

  Pictures of Work done on site

 

Block F (Alumni Block)
Update: The ground beam construction is still ongoing.
The situation with Timeline:
As of the 11th - 15th of March, the ground beam construction reached 95% completion

 Pictures of Work done on site

 

Signed,
Arc. Dapo Ojo
Project Client Representative

Adapted for publication by
Seun Abimbola
Media Officer

 

For Inquiries or to make donations

Please contact:

hostelproject@com.ui.edu.ng

provost@com.ui.edu.ng

Send a WhatsApp message to:

Provost: +2348132243158

Deputy Provost: +2348057325888